Gisborne Residents Update

This page is dedicated to keeping Gisborne residents informed about the progress of both internal and external construction at Rosalia. Here, you’ll find the latest timelines and important notices as we work to bring this development to life. If you would like to be notified of on-going updates, please fill out the form at the bottom of this page.

Stages 1 & 2

 

Details

Earthworks, drainage, service connections and installation of internal roads for the delivery of 71 lots.

Duration

Complete

Drainage Reserve

 

Details

Delivery of sediment and wetland retarding basins to cater for drainage from the Rosalia development. Landscaping will take place following civil works.

Duration

April 2025 – June 2026*

Ross Watt Road / Swinburne Avenue Intersection

Details

Upgrade of Ross Watt Road / Swinburne Avenue T-intersection, including the installation of a right-hand turning lane from Ross Watt Road travelling east into Swinburne Avenue.

Duration

Construction Complete

Swinburne Avenue Upgrade (North)

 

Details

Urbanisation of the road shoulder / installation of kerb and channel on the western side of Swinburne Avenue.

Duration

Complete

Swinburne Avenue Upgrade (South)

 

Details

Urbanisation of the road shoulder / installation of kerb and channel on the western side of Swinburne Avenue. The eastern portion is being managed by Macedon Ranges Shire Council, with Winslow Constructors appointed to deliver the works.

Duration

March 2026 – April 2026*

Cherry Lane

 

Details

Completed Phase:

Sewer outfall connection and the installation of drainage from the Rosalia development to Cherry Lane and the corner of Ormerod Court (connection runs across/down Swinburne Avenue to Cherry Lane).

Phase 1:

Cherry Lane drainage outfall works.

Phase 2:

Urbanisation of road and installation of kerb on both sides of Cherry Lane from Swinburne Avenue to Omerod Court.

Phase 3:

Urbanisation of road and installation of kerb on both sides for the remainder of Cherry Lane from Ormerod Court to Station Road.

Duration

Phase 1: April 2026 – June 2026*

Phase 2: May 2026 – July 2026*

Phase 3: July 2026 – August 2026*

*Timelines subject to change

FAQ’s

Approvals

ID_Land has sought the necessary approvals from Macedon Ranges Shire Council (MRSC) and the relevant external authorities to facilitate the above works.

Dust Management

Winslow will manage dust on site throughout the duration of works in accordance with the Construction Site and Environmental Management Plan. Water carts will be used to suppress dust on site when required, and banner mesh will be installed on construction fencing to minimise the impact to nearby residents.

Tree Protection

Tree protection fencing will be installed in accordance with MRSC approved Tree Management Plans around nearby trees for the duration of works.

Road Closures

Road closures will need to occur to facilitate the external works. Winslow will notify residents ahead of closures commencing and will maintain access to all properties. Construction vehicle access will be via the Calder Freeway and Ross Watt Road. There will be no construction vehicle access via Station Road (unless required).

Sign up to receive future Gisborne Resident Construction Updates via email

Gisborne Resident Construction Updates
Project Updates

By continuing you are agreeing to the Privacy Policy (ID_Land), Privacy Policy (Oliver Hume) and Disclaimer.